How to document your data center in Excel

Guide · 5 questions answered · updated 2026-10-15

Document a data center in Excel with one workbook and one row per thing: a Devices sheet (rack, U, model, name, power cords, what runs on it), a Power sheet (each UPS, panel, breaker and PDU with its rating and what feeds it), a Cables sheet (from, to, type, port, label) and a Racks sheet (row and position). Fill Devices first: it alone answers what is where, and each other sheet answers one more question.

Why a spreadsheet is the right start

Most documentation projects stall on data, not on tools. Everyone can open a workbook, a technician can fill it in the room, and an export from any inventory or monitoring tool lands in one. The trick is to structure it so it answers questions: where is it, what powers it, what is it connected to, what breaks if this fails.

1. Rules that save you later

  • One workbook, one sheet per kind of thing, one header row, one row per thing. No merged cells, no colour-only meaning, no totals inside the data.
  • Values only. Formulas are fine for your own checks in extra columns, but importers read values; DC Sim never evaluates formulas.
  • Names are keys. A device, rack or PDU has one name used everywhere (Devices, Cables, Power). “PDU-R05-B” in one sheet and “R5 PDU B” in another are two different things to every tool.
  • Models the way the vendor prints them. “PowerEdge R650” beats “Dell 1U”. Catalogs match on the printed model.

2. Devices: the only sheet you must have

ColumnExampleWhy
rackR05Where it is. Devices outside a rack: put the location here and leave u empty
u12The lowest U it occupies
modelPowerEdge R650Size, weight, power and airflow come from the model
namek8s-0105The key other sheets refer to
power_cordsABA, B or AB: which feed each power supply uses
runsKubernetes prod; backupsServices on the device, separated by semicolons, so a failure can name what stops
serial, owner, warranty_endMatching on re-import, and warranty alerts

Fill it top to bottom, rack by rack. When a rack is unclear, write what you see and mark it; an unknown model still places a box of the right height.

3. Power: the chain from utility to PDU

One row per node: utility, generator, ATS, UPS, panel, breaker, PDU. The columns that matter are type, rating (11 kVA, 16 A, 22 kW), fed_from (the node above) and feed (A or B). For each UPS add runtime_min from the vendor’s runtime table, or battery_kwh. With power_cords on Devices, this sheet is enough to answer “what goes dark if UPS-A fails” — see the UPS failure impact analysis.

4. Racks and rooms

rack, row and position give the real layout; height_u, width_in (10 for mini racks) and max_kw give the budgets. Template v1.3 adds an optional Rooms sheet and a room column for halls with more than one room; v1.4 adds Sites and Links for more than one site.

5. Cables: start with what fails

You do not need every patch cord on day one. Start with power cables (they make the power answer exact) and uplinks (they make the network answer exact). One row per cable: from_device, from_port, to_device, to_port, type, label. A connection through a patch panel is two rows.

6. Readings: what your monitoring already knows

If a monitoring tool measures watts or temperatures, export them as time, item, metric, value into a Readings sheet. Loads and temperatures then come from your room instead of the model’s typical values.

7. Checks to run before anyone trusts it

  • Duplicates: the same name twice, the same serial twice.
  • Overlaps: two devices claiming the same U in one rack (a device’s height counts).
  • Single points of failure: filter power_cords for A or B only; then look for AB devices whose PDUs are both on one feed.
  • Budgets: devices per rack against the rack’s max_kw; each PDU against 80 % of its rating, in normal operation and when the other feed is lost (the rack power calculator does the second one).

Importing the workbook into DC Sim runs these checks and more (port speeds, heat against cooling, phase balance, warranty ending within 12 months) and pins each one to its place in 3D.

8. Keep it current

Documentation is only worth its last update. Change the workbook with every move, add or change; keep it in one shared place; and re-check it after each change. In DC Sim a re-upload is an update: devices are matched by serial, then name, then rack and U, and you see exactly what changed before it is applied.

Step by step

6 steps

  1. List every device in the Devices sheet

    Walk the room rack by rack, top to bottom. One row per device with rack, U position and model, plus name, role and serial if you have them. Devices outside a rack get an empty U and a location in the rack column.

  2. Record the power cords

    For each device, write A, B or AB in power_cords: which feed each power supply plugs into. This one column finds most single points of failure.

  3. Map the power chain in the Power sheet

    One row per UPS, panel, breaker and PDU with its type, rating, the node that feeds it (fed_from) and its feed (A or B). Add runtime_min or battery_kwh for each UPS.

  4. Add the racks and their layout

    In the Racks sheet give each rack its row and position, and optionally room, height, width and maximum kW.

  5. Add the cables you care about

    In the Cables sheet, one row per cable: from device and port, to device and port, type, label. Start with power and uplinks; a patch-panel connection is two rows.

  6. Run the checks and keep it current

    Check for duplicate names, overlapping U positions and single-corded devices, then re-check after every change. Re-importing the workbook into DC Sim lists exactly what changed.

See it in the twin
The Devices and Cables sheets, import, checks pinned in 3D, then a re-upload with its change list (50 s).recorded in the app
What happens in this clip
  1. One file: the demo hall workbook in Excel. Devices is the only required sheet (rack, U, model, name, role, power cords, owner, warranty, what runs on it); the Cables sheet adds the cords.
  2. Import: the preview counts 121 devices, 13 racks, 910 cables and 35 power items and lists the matched models.
  3. Checks with 3D locations: U overlaps, breakers above 80 %, both power supplies on the same feed, heat above cooling.
  4. Apply: the room builds from the spreadsheet; Overview, Power (load per rack) and the Cabling view.
  5. Back in Excel one row is edited (a server moved from U2 to U30) and the file re-uploaded: the change list shows exactly what changed.
  6. End card: Download the template.
Questions people ask
What should a data center inventory spreadsheet include?

At minimum, one row per device with rack, U position and model. Add name, role, serial, owner, warranty end, which feed each power supply uses (A, B or AB) and what runs on the device. A second sheet for the power chain and a third for cables answer the failure and patching questions.

Is Excel good enough, or do I need DCIM?

For a server room or a small data center, a well-kept workbook covers inventory, the power chain and patching. What it cannot do on its own is show the room, check it, or answer what fails with what; importing it into a tool such as DC Sim adds that without retyping.

How long does it take to document a server room?

The Devices sheet takes roughly as long as walking the racks once; most of the time goes on racks nobody is sure about. Power cords and the power chain take a second pass. Exporting from an existing inventory or NetBox cuts it to minutes.

Can I use Google Sheets instead of Excel?

Yes. Export as XLSX or CSV. DC Sim imports XLSX and CSV or TSV files, reads values only, and refuses formulas, macros and encrypted files.

How do I keep the spreadsheet up to date?

Change the sheet with every move, add or change, and re-check it. If you import it into DC Sim, a re-upload is an update: devices are matched by serial, then name, then rack and U, and you see a change list before anything is applied.

One Excel file. Your room in 3D.

Download the import template (v1.4, eleven sheets, only Devices required) and the filled example from our demo hall. No form, no email needed, no macros in the files.

Fill in the Devices sheet and send it with your walkthrough request; we import it on the call. What each sheet does