Imagined — a fictional design built from public numbers. No operator plans this.

Imagined giant · Solar + storage compute hub (East-Data-West-Computing context)

Imagined 1 GW solar compute hub — Gobi

Solar + storage compute hub (East-Data-West-Computing context): 1,002 MW IT, 546,048 GPUs, PUE 1.17 — designed by us, checked by the engine

15 s flight, recorded in DC Simimagined · simulated

The story

An imagined 1 GW compute hub in the Gobi near Jiuquan, in the spirit of the East-Data-West-Computing plan: 4 halls, 79 pods of 96 GB200 NVL72 rack systems, dry coolers in a plateau climate with a 14 °C daily swing, and a 2 GW solar field with 4 GWh of batteries next door. The engine gives PUE 1.17 at a summer afternoon; the national backbone links it to Qingyang, Xi'an, Beijing and Shanghai.

The numbers

IT1,002 MW
Total facility1,174 MW
PUE1.17
Halls / pods4 / 79
Racks / GPUs7,584 / 546,048
Tokens per second (estimated)2,227,780,487
Tokens per kWh (IT, estimated)8,002,362
Energy per year10,284,240 MWh · about $3,291 M at 0.32 USD/kWh
CO₂ per year822,739 t at 80 g/kWh
Water (consumptive)0 m³/day — closed-loop dry coolers: no consumptive water; evaporative trim on the hottest days is not modelled
Catalog BOM per pod$7,860,650 at list prices; not included (no public list price): NVIDIA GB200 NVL72 × 96, Arista 7060X5-64D × 8, Arista 7800R3 Modular Chassis × 2

engine on the representative hall (hall.json) at 15:00 local, mid-July, scaled by the pod count; rounded. Token figures are engine estimates, not benchmarks. Energy and CO₂ use the tariff and grid factor in the references below.

The representative hall

The representative hall of Imagined 1 GW solar compute hub — Gobi, modelled with catalog devices in DC Sim
One hall modelled device by device; the other halls are scaled from itimagined · simulated

Notable

  • 79 pods × 96 GB200 NVL72 rack systems (120 kW each from the catalog) = 546,048 GPUs.
  • Per pod the engine sees 12,686.1 kW IT, 14,864.5 kW facility, PUE 1.17 and 28,199,753 tokens/s at the design afternoon.
  • 24 CoolIT CHx750 CDUs per pod carry 70 % of the heat as liquid; Vertiv Liebert CW CRAHs take the rest.
  • A year at 0.32 CNY/kWh: ¥3291 M for 10,284,240 MWh; 823 kt CO₂ at 80 g/kWh.
  • Catalog list prices cover 5 of 8 part types per pod; the GB200 NVL72 has no list price in the catalog, so the BOM leaves it out.

What would break (engine)

  • Substation trip (utility lost for 15 minutes): Rides through. lowest UPS runtime 10 min. (Substation (400 kV, imagined) lost power (+6 more); UPS bank A on battery · 10 min left (+3 more))
  • CDU loop leak at a rack manifold (6 L/min): Outage. 1 devices lose power or trip (72 GPUs); 1.4 L released before isolation; 254.4 M tokens lost. (Leak at Manifold R001 · 0 L released; Manifold R001 isolated after leak; nvl72-r001 throttled to 20 %; nvl72-r001 thermal shutdown)
  • Trunk cable cut (GBS-1 ↔ XIY-POP): GBS-1 ↔ XIY-POP cut, not protected — 2240 Gb/s rerouted via QY-HUB–XIY-POP, GBS-1–QY-HUB (17 ms instead of 16.6)

What we assumed and why

  • Scale: 1,000 MW IT target from the brief (IMAGINED-GIANTS.md §1); the pod count is that target ÷ the engine's pod IT load.
  • Rack system: catalog record rack_system/nvidia/gb200-nvl72, 120 kW IT, 72 GPUs, 70 % liquid-cooled (catalog thermal data).
  • Cooling: cdu/coolit/chx750 CDUs (750 kW, catalog) in loops of 3 per row, N+1; heat rejected to dry coolers; crah/vertiv/liebert-cw CRAHs (120 kW) on a chilled-water plant for the air share.
  • Power: 2N from a 400 kV substation through ATS (grid / genset bank), transformers, switchboards and MW-class UPS banks (generic nodes: no MW-class UPS in the catalog), busway taps per rack; standby genset banks of Cat 3516C (2 MW standby, catalog); 2 GW solar PV + 4 GWh battery storage (as a site summary; diesel standby in the hall model).
  • Climate: a July day at 22 °C mean with a 14 °C daily swing and 35 % RH (typical July climate for the region); the numbers are read at 15:00 local, the warmest hour.
  • Grid factor 80 g CO₂/kWh and tariff 0.32 CNY/kWh: dc-world/reports/giants-references.md §2 / §3.
  • Tokens: every rack serves a 70B chat model at 70–95 % load (engine estimate from GPU memory bandwidth and FLOPS; labelled estimated, not a benchmark).
  • Water: closed-loop dry coolers, no consumptive water (evaporative trim not modelled).
  • Estate: the DR and peer sites, link capacities and carriers are part of the imagined design, not real contracts; latency is estimated from distance.
  • References for scale, cooling and power patterns: §1.7 东数西算 hubs: Qingyang PUE < 1.15, 0.28–0.38 RMB/kWh, free-air plateau climate; §1.6 Zhangbei: free-air cooling up to 300 days/year; §2.4 Northwest grid 560–620 g/kWh; green PPA ~50–120 g/kWh (dc-world/reports/giants-references.md).

The estate

GBS-1QY-HUBXIY-POPPEK-POPSHA-POP
Imagined 1 GW solar compute hub — Gobi: 5 sites, 5 links (imagined)map: Natural Earth (public domain)
FromToTypeBandwidthProtectedEst. one-way latency
GBS-1QY-HUBbackbone12,800 Gbpstrue≈ 6.8 ms
GBS-1XIY-POPbackbone6,400 Gbpsfalse≈ 8.3 ms
QY-HUBXIY-POPbackbone6,400 Gbpstrue≈ 1.6 ms
XIY-POPPEK-POPbackbone12,800 Gbpstrue≈ 6.8 ms
XIY-POPSHA-POPbackbone12,800 Gbpstrue≈ 9.2 ms

Open it on the earth: cut a link, lose a site

Files

  • estate.xlsx — Sites and Links (DC Sim template v1.4)
  • hall.xlsx — the representative hall, device by device
  • giant.json — the record with derived numbers and assumptions

Public reference numbers: mega-campus references. CC BY 4.0. Imagined — a fictional design built from public numbers.

Questions people ask
Is Imagined 1 GW solar compute hub — Gobi a real data center?

No. Imagined — a fictional design built from public numbers. No operator plans it; it shows what such a campus would need, using catalog devices and public reference numbers.

Where do the numbers come from?

engine on the representative hall (hall.json) at 15:00 local, mid-July, scaled by the pod count; rounded. Assumptions and the public references are listed on this page.

What happens if substation trip (utility lost for 15 minutes)?

Rides through. lowest UPS runtime 10 min.