Imagined giant · AI factory campus

Imagined 5 GW AI factory — Gulf Coast

AI factory campus: 5,001 MW IT, 2,681,856 GPUs, PUE 1.17 — designed by us, checked by the engine

15 s flight, recorded in DC Simimagined · simulated

The story

An imagined AI factory on empty land on the US Gulf Coast: 8 halls, 388 identical pods of 96 GB200 NVL72 rack systems, 2,681,856 GPUs. The grid arrives at 400 kV; gas turbines and batteries carry it through outages. Each pod's racks are cooled 70 % by liquid (CDUs to dry coolers) and 30 % by air. At a summer afternoon the engine finds 5,001 MW of IT, PUE 1.17 and 11,146 million tokens a second from a 70B model — and 21.6 million tonnes of CO₂ a year on today's grid mix.

The numbers

IT5,001 MW
Total facility5,859 MW
PUE1.17
Halls / pods8 / 388
Racks / GPUs37,248 / 2,681,856
Tokens per second (estimated)11,146,005,772
Tokens per kWh (IT, estimated)8,023,978
Energy per year51,324,840 MWh · about $3,336 M at 0.065 USD/kWh
CO₂ per year21,556,433 t at 420 g/kWh
Water (consumptive)0 m³/day — closed-loop dry coolers: no consumptive water; evaporative trim on the hottest days is not modelled
Catalog BOM per pod$7,860,650 at list prices; not included (no public list price): NVIDIA GB200 NVL72 × 96, Arista 7060X5-64D × 8, Arista 7800R3 Modular Chassis × 2

engine on the representative hall (hall.json) at 15:00 local, mid-July, scaled by the pod count; rounded. Token figures are engine estimates, not benchmarks. Energy and CO₂ use the tariff and grid factor in the references below.

The representative hall

The representative hall of Imagined 5 GW AI factory — Gulf Coast, modelled with catalog devices in DC Sim
One hall modelled device by device; the other halls are scaled from itimagined · simulated

Notable

  • 388 pods × 96 GB200 NVL72 rack systems (120 kW each from the catalog) = 2,681,856 GPUs.
  • Per pod the engine sees 12,888.4 kW IT, 15,100.5 kW facility, PUE 1.17 and 28,726,819 tokens/s at the design afternoon.
  • 24 CoolIT CHx750 CDUs per pod carry 70 % of the heat as liquid; Vertiv Liebert CW CRAHs take the rest.
  • A year at 0.065 USD/kWh: $3336 M for 51,324,840 MWh; 21,556 kt CO₂ at 420 g/kWh.
  • Catalog list prices cover 5 of 8 part types per pod; the GB200 NVL72 has no list price in the catalog, so the BOM leaves it out.

What would break (engine)

  • Substation trip (utility lost for 15 minutes): Rides through. lowest UPS runtime 9 min. (Substation (400 kV, imagined) lost power (+6 more); UPS bank A on battery · 10 min left (+3 more))
  • CDU loop leak at a rack manifold (6 L/min): Outage. 1 devices lose power or trip (72 GPUs); 1.4 L released before isolation; 254.9 M tokens lost. (Leak at Manifold R001 · 0 L released; Manifold R001 isolated after leak; nvl72-r001 throttled to 20 %; nvl72-r001 thermal shutdown)
  • Trunk cable cut (GCX-1 ↔ HOU-IX): GCX-1 ↔ HOU-IX cut — traffic on the protection path, +0.6 ms

What we assumed and why

  • Scale: 5,000 MW IT target from the brief (IMAGINED-GIANTS.md §1); the pod count is that target ÷ the engine's pod IT load.
  • Rack system: catalog record rack_system/nvidia/gb200-nvl72, 120 kW IT, 72 GPUs, 70 % liquid-cooled (catalog thermal data).
  • Cooling: cdu/coolit/chx750 CDUs (750 kW, catalog) in loops of 3 per row, N+1; heat rejected to dry coolers; crah/vertiv/liebert-cw CRAHs (120 kW) on a chilled-water plant for the air share.
  • Power: 2N from a 400 kV substation through ATS (grid / genset bank), transformers, switchboards and MW-class UPS banks (generic nodes: no MW-class UPS in the catalog), busway taps per rack; standby genset banks of Cat 3516C (2 MW standby, catalog); on-site gas turbines + batteries (sized as the genset bank in the model).
  • Climate: a July day at 29 °C mean with a 9 °C daily swing and 70 % RH (typical July climate for the region); the numbers are read at 15:00 local, the warmest hour.
  • Grid factor 420 g CO₂/kWh and tariff 0.065 USD/kWh: dc-world/reports/giants-references.md §2 / §3.
  • Tokens: every rack serves a 70B chat model at 70–95 % load (engine estimate from GPU memory bandwidth and FLOPS; labelled estimated, not a benchmark).
  • Water: closed-loop dry coolers, no consumptive water (evaporative trim not modelled).
  • Estate: the DR and peer sites, link capacities and carriers are part of the imagined design, not real contracts; latency is estimated from distance.
  • References for scale, cooling and power patterns: §1.1 Stargate Abilene (scale, DLC + CDUs, PUE 1.12–1.15); §1.2 Hyperion & Prometheus (GW campus, 500 kV, gas backstop); §1.3 Colossus (on-site turbines + BESS, 100k GPUs in one fabric); §2.1 ERCOT grid factor ~400 g/kWh and ~$0.065/kWh (dc-world/reports/giants-references.md).

The estate

GCX-1GCX-DRHOU-IXASH-IX
Imagined 5 GW AI factory — Gulf Coast: 4 sites, 4 links (imagined)map: Natural Earth (public domain)
FromToTypeBandwidthProtectedEst. one-way latency
GCX-1HOU-IXdark fibre25,600 Gbpstrue≈ 0.9 ms
GCX-1GCX-DRdark fibre12,800 Gbpstrue≈ 1.8 ms
HOU-IXASH-IXwavelength10,000 Gbpstrue≈ 14.5 ms
GCX-DRHOU-IXwavelength3,200 Gbpsfalse≈ 2.3 ms

Open it on the earth: cut a link, lose a site

Files

  • estate.xlsx — Sites and Links (DC Sim template v1.4)
  • hall.xlsx — the representative hall, device by device
  • giant.json — the record with derived numbers and assumptions

Public reference numbers: mega-campus references. CC BY 4.0. Imagined — a fictional design built from public numbers.

Questions people ask
Is Imagined 5 GW AI factory — Gulf Coast a real data center?

No. Imagined — a fictional design built from public numbers. No operator plans it; it shows what such a campus would need, using catalog devices and public reference numbers.

Where do the numbers come from?

engine on the representative hall (hall.json) at 15:00 local, mid-July, scaled by the pod count; rounded. Assumptions and the public references are listed on this page.

What happens if substation trip (utility lost for 15 minutes)?

Rides through. lowest UPS runtime 9 min.