Skip to content

Landover Mall data center: why Prince George's County paused the project

Guide · 5 questions answered · updated 2026-11-14

The Landover Mall data center, a $5 billion campus planned at Brightseat Park in Prince George's County, Maryland, is stalled. In October 2026 the County Council passed a bill that sends the application back for a council vote, closing a 2021 shortcut, WTOP reported. A county moratorium and a petition with more than 25,000 signatures came first.

An empty former mall site with a perimeter fence and a county council hearing sign

The Landover Mall data center, a $5 billion campus planned at Brightseat Park in Prince George’s County, Maryland, is stalled. In October 2026 the County Council passed a bill that sends the application back for a council vote, closing a 2021 shortcut, WTOP reported. A county moratorium and a petition with more than 25,000 signatures came first.

1. What changed in Prince George’s County

WTOP reported in October 2026 that the county council had voted in 2021 to take itself out of the approvals process for data centers, to speed construction. Council member Shayla Adams Stafford, whose district includes the site, called that a loophole that allowed the Brightseat Park development to go forward. The new law requires the application to go before the council again, which she said essentially kills it given the opposition.

The same bill changes the process for every future application: detailed site plans that consider how surrounding land is used, a more in-depth public review, and a council say on each project. WTOP says the legislation was a response to opposition to the Landover project, which led to the county’s first data center moratorium in 2025. Council members said at the time that they had been unaware of the plans until it was almost too late.

WJLA 7News (2 November 2026, updated 9 November) adds that the council vote came roughly three months after county leaders extended the moratorium. Beth Landry of the CCAN Action Fund told the station the project should follow any new building standards, if and when the moratorium is lifted, instead of the old permitting rules. WJLA’s own reading: the project is not officially dead, but its path forward is much harder.

2. The site and the timeline

YearWhat happenedReported by
1972Landover Mall opensWJLA 7News
2002Mall closes; the site stays mostly vacantWJLA 7News, NPR
2014Sears, the last major store, closesWJLA 7News
2021Council takes itself out of data center approvalsWTOP
2024County planners approve a $5 billion data center campusNPR
2025First county moratorium on data center developmentWTOP
2026Moratorium extended; about three months later the council passes the billWJLA 7News, WTOP

NPR describes nearly 90 acres of empty land, with the development able to occupy more than 80 acres. NPR also says the project had been set to break ground between 2026 and 2027.

3. What residents objected to

NPR’s profile of 7 November 2026 follows Taylor Frazier McCollum, who lived less than a mile from the site when she heard about the plan. Her objection, in her words to NPR, was to “water-polluting, diesel-generating data centers right down the street from where people live, work, play.” Her petition gathered more than 25,000 signatures and led to well attended protests and several local moratoriums.

Her coalition, NPR writes, mixed socialists, environmentalists, people angry about their electric bills and neighbors new to organizing. Staci Hartwell, a longtime local environmental activist, told NPR she had struggled for years to get traction on the issue. NPR puts the national count at about 500 data center moratoriums, while noting that estimates vary.

Water is a recurring point in these fights; our guide on AI data center water use per day explains what drives the number.

4. The revenue side

The county needs the money. NPR lists the pressures: a local Six Flags closed last year, the Washington Commanders plan to return to Washington, D.C., thousands of federal workers have lost their jobs, and the county faces a budget deficit. At a council meeting in September, council member Wanika Fisher, who supports moving some data center projects forward, said “Our county has an economic future that we have to grapple with” and that a data center is “worth the hard discussion.”

Frazier McCollum has pitched a sports complex, affordable housing or heritage tourism for the site, and acknowledged to NPR that none would be as lucrative as a data center campus. The same tension between tax income and neighbors shows up in the Kraft Group plan for Sutton, Massachusetts.

5. What site planners can take from Landover

These points are our reading of the case, not findings from the reporting.

  • An approval granted under a fast track can be reopened. Check how a jurisdiction’s approval path was created and whether a council can pull it back, as Prince George’s did with its 2021 change.
  • Distance to homes drives the reaction. At less than a mile from residents, generators and water use became the core complaints. Publish generator, noise, water and lighting plans before the first hearing, not after the petition.
  • Budget for moratorium risk. The county moved from no moratorium to a moratorium, an extension and a new review law within about two years.
  • A large vacant retail site looks like an easy win on paper. Here the acreage was there, but the neighbors were too.

Similar opposition has shaped rules elsewhere: see our guides on Ohio data center ballot measures and the Amsterdam data center protest.

Questions people ask
Why is the Landover Mall data center project stalled?

WTOP reported in October 2026 that the Prince George's County Council passed legislation requiring the project to return for council approval, closing a 2021 change that had taken the council out of data center approvals.

Where is the proposed Landover data center located?

WJLA 7News reported on 2 November 2026 that the Brightseat Park project sits along Brightseat Road at the demolished Landover Mall site in Landover, Maryland.

What community concerns were raised against the campus?

NPR reported on 7 November 2026 that residents living less than a mile away objected to diesel generators and water pollution from a data center campus close to where people live, work and play.

How large is the Landover Mall development site?

NPR reported on 7 November 2026 that the former mall site covers nearly 90 acres, with the proposed data center campus designed to occupy more than 80 acres.

How many data center moratoriums have been enacted in the United States?

NPR reported on 7 November 2026 that community opposition has prompted approximately 500 data center moratoriums nationwide, although estimates vary.

One Excel file. Your room in 3D.

Download the import template (v1.5, twelve sheets, only Devices required) and the filled example from our demo hall. No form, no email needed, no macros in the files.

Fill in the Devices sheet and send it with your walkthrough request; we import it on the call. What each sheet does